Hi all- I am sorry to do this but I have a change to the AutoGOLE diagram. It was decided over the weekend that since there was such a short runway to prepare, that both WIX and MAX decided to bow out of the NSI+GLIF SC demos. And so they requested that we not include them in the various demo flyers. So attached is an updated diagram of the AutoGOLE. The only modification from the v8 diagram to the v9 diagram is the deletion of the two networks. All other NSI exchange points remain in the same location on the diagram. Please look at the accompanying flyer and diagram and if you have any last minute changes - you need to get them to me asap. I will try to print up new flyers in time for tomorrow morning. Last call! Thanks! Jerry PS - sorry these are big files.
As long as we're making last-minute changes: the GEANT-Netherlight link is now actually up it seems. I do not have US-LHCnet topologies. Did you make them? Jeroen. On 12 Nov 2012, at 10:12, Jerry Sobieski <jerry@nordu.net> wrote:
Hi all-
I am sorry to do this but I have a change to the AutoGOLE diagram. It was decided over the weekend that since there was such a short runway to prepare, that both WIX and MAX decided to bow out of the NSI+GLIF SC demos. And so they requested that we not include them in the various demo flyers.
So attached is an updated diagram of the AutoGOLE. The only modification from the v8 diagram to the v9 diagram is the deletion of the two networks. All other NSI exchange points remain in the same location on the diagram.
Please look at the accompanying flyer and diagram and if you have any last minute changes - you need to get them to me asap. I will try to print up new flyers in time for tomorrow morning.
Last call! Thanks! Jerry
PS - sorry these are big files.
<Supercomputing2012-SLC AutomatedGOLE v9.pptx><Supercomputing2012-SLC AutomatedGOLE v9.pdf><AutoGOLE SC12 handout-v1.pdf>
I've brought up the ESNet NSI at http://jupiter.es.net:8288/ConnectionService right now it won't quite follow the state transitions but I hope to have it done within the day is that OK? On Nov 12, 2012, at 9:24 AM, Jeroen van der Ham wrote:
As long as we're making last-minute changes: the GEANT-Netherlight link is now actually up it seems.
I do not have US-LHCnet topologies. Did you make them?
Jeroen.
On 12 Nov 2012, at 10:12, Jerry Sobieski <jerry@nordu.net> wrote:
Hi all-
I am sorry to do this but I have a change to the AutoGOLE diagram. It was decided over the weekend that since there was such a short runway to prepare, that both WIX and MAX decided to bow out of the NSI+GLIF SC demos. And so they requested that we not include them in the various demo flyers.
So attached is an updated diagram of the AutoGOLE. The only modification from the v8 diagram to the v9 diagram is the deletion of the two networks. All other NSI exchange points remain in the same location on the diagram.
Please look at the accompanying flyer and diagram and if you have any last minute changes - you need to get them to me asap. I will try to print up new flyers in time for tomorrow morning.
Last call! Thanks! Jerry
PS - sorry these are big files.
<Supercomputing2012-SLC AutomatedGOLE v9.pptx><Supercomputing2012-SLC AutomatedGOLE v9.pdf><AutoGOLE SC12 handout-v1.pdf>
ESnet NSI uPA is up (in the bare nick of time) running NSI v2. Reserve / provision / release / terminate lifecycle works fine & verified with the AIST folks. Query does not quite work right now - it will respond to query requests but with an empty list. Neither does modify. On Nov 12, 2012, at 9:26 AM, Vangelis Chaniotakis wrote:
I've brought up the ESNet NSI at
http://jupiter.es.net:8288/ConnectionService
right now it won't quite follow the state transitions but I hope to have it done within the day
is that OK?
On Nov 12, 2012, at 9:24 AM, Jeroen van der Ham wrote:
As long as we're making last-minute changes: the GEANT-Netherlight link is now actually up it seems.
I do not have US-LHCnet topologies. Did you make them?
Jeroen.
On 12 Nov 2012, at 10:12, Jerry Sobieski <jerry@nordu.net> wrote:
Hi all-
I am sorry to do this but I have a change to the AutoGOLE diagram. It was decided over the weekend that since there was such a short runway to prepare, that both WIX and MAX decided to bow out of the NSI+GLIF SC demos. And so they requested that we not include them in the various demo flyers.
So attached is an updated diagram of the AutoGOLE. The only modification from the v8 diagram to the v9 diagram is the deletion of the two networks. All other NSI exchange points remain in the same location on the diagram.
Please look at the accompanying flyer and diagram and if you have any last minute changes - you need to get them to me asap. I will try to print up new flyers in time for tomorrow morning.
Last call! Thanks! Jerry
PS - sorry these are big files.
<Supercomputing2012-SLC AutomatedGOLE v9.pptx><Supercomputing2012-SLC AutomatedGOLE v9.pdf><AutoGOLE SC12 handout-v1.pdf>
_______________________________________________ nsi-wg mailing list nsi-wg@ogf.org https://www.ogf.org/mailman/listinfo/nsi-wg
Guys, Sorry about the mass e-mail, but I wasn't sure which to target. I have added the Geant STP to Netherlight. <hasSTP rdf:resource="urn:ogf:network:stp:netherlight.ets:geant-80"/> <hasSTP rdf:resource="urn:ogf:network:stp:netherlight.ets:geant-81"/> <hasSTP rdf:resource="urn:ogf:network:stp:netherlight.ets:geant-82"/> <hasSTP rdf:resource="urn:ogf:network:stp:netherlight.ets:geant-83"/> John. ----- Original Message -----
From: "Jerry Sobieski" <jerry@nordu.net> To: automatedgole-pilot@internet2.edu, nsi-wg@ogf.org Sent: Monday, November 12, 2012 12:12:21 PM Subject: [Nsi-wg] AutoGOLE diagram v9
Hi all-
I am sorry to do this but I have a change to the AutoGOLE diagram. It was decided over the weekend that since there was such a short runway to prepare, that both WIX and MAX decided to bow out of the NSI+GLIF SC demos. And so they requested that we not include them in the various demo flyers.
So attached is an updated diagram of the AutoGOLE. The only modification from the v8 diagram to the v9 diagram is the deletion of the two networks. All other NSI exchange points remain in the same location on the diagram.
Please look at the accompanying flyer and diagram and if you have any last minute changes - you need to get them to me asap. I will try to print up new flyers in time for tomorrow morning.
Last call! Thanks! Jerry
PS - sorry these are big files.