Mathias Dalheimer wrote:
There is no way of supporting e.g. coallocation of resources in the RSS.
That's not quite true. Provided there is a way of expressing it (JSDL does not give us enough) coallocation can be supported by the EPS, though it would just be returning possible coallocation plans and not ones backed up by hard reservations. (As you said in text I elided, that is stuff that is up to the job manager and reservation service). Just as with the CSG, arranging for the EPS to return an ordered set of plans is likely to be the right approach, especially as it allows the JM to decide what to do if the first plan falls through (and different plans might be needed depending on exactly what happened too). Donal.