Dear all

Please take this as a straw-man – really just to get comments from the experts.

 

Here is the list of External Milestones from out web site:

July 2002

Begin work on tools classification

Oct 2002

Near-final draft of performance characteristics hierarchy document to GFSG

Mar 2003

Finish work on tools classification web page (Done.)

Mar 2003

Begin work on schema document

Apr 2003

Submit performance characteristics document to GFSG (Done.)

Nov 2003

First draft of schema document (Done.)

June 2004

Submit schema document to GFSG

 

 

I suggest we modify / add something like (Need to get the dates correct I guess):

Oct 2004 Version 1 Schema in Draft

May 2005 Document for Version 1 Schema ready for discussion (assuming we do that after consulting at GGF13)

May 2005 Pilot Demonstrations of Version 1 Schema

Jun 2005 Initial Draft of Version2 Schema ready for discussion at GGF14 (maybe this is too detailed and should be in the internal milestones)

 

Dec 2005 Version2 Schema ready for GFSG

???

 

The list of internal Milestones from GGF11 is:

u     Oct 2003          Draft XML

u     Oct 2003          f2f discussion on XML and Schema

u     Oct 2003   GGF 9 Chicago

u     Dec 3003          Agreed version of Schema document (data model)

u     Jan 2003          Create XML Schema Request & Report/Response

u     Apr 2003          Submit hierarchy document to GFSG (done Jul 03 )

u     Nov 2003          Draft of Schema document

u     Jan 2004          Initial implementations and Proof of Concept Demos

u     Mar 2004  GGF 10 Berlin

u     Apr 2004          Finish v2 of XML Schema request & response

u     Xxx 2004          Match with Requirements doc.

u     Apr 2004          Draft request and response of Metadata (in progress)

u     Xxx 2004          Implement XML-RPC and Document/Literal PoC (in progress)

u     Xxx 2004          Test implementations and Proof of Concept Demos (in progress)

u     Jun 2004  GGF 11 Hawaii

u     Jun 2004          NM_RG BoF

u     Jun 2004          Submit schema document to GFSG (take note of implementations)

u     Sep 2004  GGF 12 Brussels

u     Xxx 2004          Submit request & response requirement documents to GFSG

 

The underlined as the external Milestones.

 

Nov 2004 Pilot implementations of version 1 Schema started? Operational? In Internet2 EGEE and Dante

Dec 2004 Work started on Verstion2 Schema

Mar 2005 First Demonstrations of Version 1 Schema

 

Mar 2005 GGF 13 Seoul

May 2005 Document for Version 1 Schema ready for discussion (assuming we do that after consulting at GGF13)

May 2005 Pilot Demonstrations of Version 1 Schema ie basically up and running

 

Xxx 2005 Version 2 Schema ??

Jun 2005 GGF 14 Chicago

 

Xxx 2005 Version 2 Schema Discussion of results of Pilots ??

 

Oct 2005 GGF 15 Boston

Xxx 2005 Version 2 Schema  recommendation doc ??

 

Regards

Richard Hughes-Jones

 

Tel:  +44 (0) 161 275 4117

Fax: +44 (0) 161 273 5867