Attended: Dejan, Ayla, Stuart, Satish and Guilherme
1. Updates
UFCG:
Continuing the interoperability tests against NEC and HP. But, NEC
endpoint still has the 'hang-after-run' issue. Ayla has contacted
Satish regarding this issue. She is likely to finish the tests today.
NEC:
CDL implementation of 'delegate' and 'wait' are done and the CDLs are
ready. Will complete the 'switch' case very soon. After the CDL
implementations, Satish will resolve the tomcat server issue that UFCG
has reported.
Softricity:
Stuart is working on getting his endpoint ready for testing. According
to him, it may take some time as it needs some more testing. Will soon
post the interoperability test results.
2. Interoperability document
Ayla has started the document and according to Guilherme, not sure if she has committed the doc.
Satish has also started composing the document and will have it ready
by the start of next week.
Stuart will look into the document scope and see if he can complete it
before 7th July.
Dejan said the deadline for this document is July 7th and it's
important for everybody to stick to the deadline.
3. GGF at Washington
Dejan said during this conf. we can meet and hopefully close all the CDDLM activities officially .